Timeline.

We intend to submit a planning application for the new energy recovery facility at Westmill sometime in 2011.

  • If the application is approved by the end of 2012 construction should begin in 2013.
  • Completion of the construction work is likely to take approximately three years
  • The energy recovery facility could start to accept waste during 2016.